When sounding a pole, where should you start?

Prepare with SWLCAT Book 1-2 to excel in the licensing test. Flashcards and multiple-choice questions with explanations aid learning. Experience exam readiness!

Starting at ground level when sounding a pole is essential for accurately assessing the condition and integrity of the structure. This approach allows for a thorough evaluation of the entire pole, beginning with its base where issues like rot, decay, or structural weakness are often most prevalent. By beginning from the ground, you can detect any abnormalities or deterioration that may not be visible higher up on the pole. This method also promotes safety, as it ensures that you are grounded and stable before lifting your attention to higher parts of the pole. Consequently, this practice sets a solid foundation for a comprehensive inspection, ultimately contributing to the structural integrity and safety of the entire installation.